Okay, let's have a look at
risk management in practice
-
And what I want to do
is to start with some basic concepts
-
then focus on two difficult areas
in the risk process
-
So, I guess if I asked you
to define the word 'risk'
-
you would have some ideas
of what it meant
-
We might not have a formal definition
that we could quote,
-
but we all have something in our minds
when we hear the word 'risk'
-
This is what we think,
and maybe you think of things like this
-
Maybe you feel like this little guy,
facing some big ugly challenge
-
that you know is just going to
squash you flat.
-
Maybe you feel like this guy.
-
This is a real job in North Korea,
-
and his job is to hold the target
for other people to shoot at
-
Sometimes project managers
have the target here
-
We feel like everybody is shooting at us
in our job
-
Or maybe you just know there's something
nasty out there, waiting to get you
-
And maybe that's what you think of
when you think of the word 'risk'
-
Well that's partly true
but it's not the whole truth.
-
Risk is not the same
as uncertainty.
-
Risk is related to uncertainty
but they're different.
-
So all risks are uncertain
but not all uncertainties are risks.
-
If you have a risk register
or a risk list,
-
you don't have a million items in it,
or you shouldn't.
-
You don't even probably have
a thousand items in it,
-
you have a smaller number.
-
Although there are millions
of uncertainties in the world.
-
So how do we decide which uncertainties
we're going to call 'risk'?
-
And write them down
and put them in our risk register
-
and decide to do something about them.
-
Clearly 'risk' is a subset
of uncertainties, but which subset?
-
How do you know?
-
I think it's very simple to separate
risk and uncertainty.
-
And I used 3 English words,
-
these words here,
'risk is uncertainty that matters."
-
Because most of the
uncertainties in the world don't matter.
-
We don't care if it's going to rain
in London tomorrow afternoon.
-
It might, it might not,
it's irrelevant, it doesn't matter.
-
We don't care what the
exchange rate will be
-
if it's between the Russian Ruble
and the Chinese Yen in 2020.
-
It doesn't matter to us.
-
But there are things on our projects,
-
and things in our families,
-
and things in our country,
-
which are uncertain which do matter to us.
-
If it's an uncertainty that matters,
it's a risk.
-
So here's another question,
how do you know what matters?
-
In your projects,
what are the things that matter?
-
The things that matter in our projects
are our objectives.
-
Not Synced
So we must always connect uncertainty
with objectives,
-
Not Synced
in order to find the risks.
-
Not Synced
And if we look at
some definitions of risk,
-
Not Synced
this is the ISO standard that I mentioned,
-
Not Synced
it connects those words very simply.
-
Not Synced
Risk is the effect on uncertainty
on objectives.
-
Not Synced
And we might look at another definition
from the UK,
-
Not Synced
from our association
with project management,
-
Not Synced
it says the same thing that risk
is an uncertain event
-
Not Synced
or a set of circumstances,
which is uncertain,
-
Not Synced
but it matters because should it occur,
-
Not Synced
it will have an effect on achievement of objectives.
-
Not Synced
Uncertainty that matters.
-
Not Synced
So we should be looking
in our risk register for two things.
-
Not Synced
Is it uncertain? We don't want
problems in our risk register.
-
Not Synced
We don't want issues in the risk register.
-
Not Synced
We don't want constraints or requirements.
-
Not Synced
These things are certain,
what we want are uncertainties,
-
Not Synced
something that might happen
or might not happen.